The Tianjin International Airport Tunnel No. 1 Project cross strata such as silty clay, muddy clay, and fine sand. A mobile underground mixing station solution was implemented for the shield construction.

 

An additional No. 6 platform was equipped with a double-liquid grouting mixing station (integrated storage, mixing, and pumping unit), significantly reducing the cost of grout transport vehicles.

 

Excavation diameter: 13.8m 
Segment O.D.:13.3m
Total Length: 2.93 km
Grouting Capacity: 30 m³/h
Date: 2023